Project Dates Page of the New Project Wizard

Use the Project Dates page to enter key dates for the project.

Contents

Field Description
Baseline Start The Baseline Start date is the initial status date of the project. This date defaults to the status date of the calendar assigned to the project.
Baseline Finish The Baseline Finish date is the last date of the project. This date defaults to latest date defined in the calendar assigned to the project.
Forecast Finish The Forecast Finish date is the forecasted finish date in the calendar assigned to the project.